CHINA: The National Development & Reform Commission has approved metro plans in three cities.
Qingdao's second phase of metro development would add 181·7 km to the 50 km first phase now under construction; 40% of the cost is to be met by the government. All planned lines will be operated with six-car Type B trainsets running at up to 80 km/h, with a maximum speed of 120 km/h on Line 8.
Qingdao metro second phase | |||||
---|---|---|---|---|---|
Line | Route | Length km | Stations | Cost bn yuan | Construction timescale |
1 | Emeishanlu – Xingguolu | 42·7 | 29 | 26·81 | 2015-20 |
4 | Renmin Huitang – Dahedonglu | 30·7 | 25 | 21·10 | 2016-20 |
6 Phase 1 | Xindunlu – Shengtaiyuan | 30·3 | 20 | 17·90 | 2017-21 |
7 Phase 1 | Xingguolu – Dongguozhuang | 17·3 | 12 | 10·70 | 2015-20 |
8 | Jiaozhoubei – Wusi Guangchang | 60·7 | 16 | 31·40 | 2016-21 |
The third phase of the Chengdu metro would add 124·2 km and five lines, taking the network to 508 km by 2020. The lines would be operated using six-car Type A trainsets, with a maximum speed of 80 km/h on Line 8 and 100 km/h on the other lines. The city is to fund one-fifth of the project cost.
Chengdu metro third phase | |||||
---|---|---|---|---|---|
Line | Route | Length km | Stations | Cost bn yuan | Construction timescale |
8 Phase 1 | Changchenglu – Shilidian | 27·4 | 22 | 21·83 | 2016-20 |
9 Phase 1 | Jindun Zhongxin – Lianghe Senlin Gongyuan | 23·7 | 11 | 16·68 | 2017-20 |
10 Phase 2 | Airport Terminal 2 – Taipingsi | 26·7 | 9 | 13·16 | 2016-19 |
11 Phase 1 | Guandonglu – Huilonglu | 20·7 | 18 | 16·51 | 2016-19 |
17 Phase 1 | Jiyouzhen – Yiyuan | 25·7 | 9 | 14·95 | 2017-20 |
The NDRC has also approved the second phase of the Guiyang metro, which would add 114·1 route-km by 2022. Guizhou province and Guiyang city will meet 30% of the cost. All lines would use six-car Type B trainsets with maximum speeds of 100 km/h (lines 2 and 3) or 80 km/h (lines S1 and S2).
Guiyang metro second phase | |||||
---|---|---|---|---|---|
Line | Route | Length km | Stations | Cost bn yuan | Construction timescale |
2 Phase 2 | Youjiajie – Shuiyanba | 12·8 | 8 | 8·48 | 2017-22 |
3 Phase 1 | Dongfengzhen – Sheng Dianzigongye Xueyuan | 40·7 | 26 | 28·43 | 2016-21 |
S1 Phase 1 | Wangchengpo – Gui’an | 28·5 | 12 | 15·48 | 2016-20 |
S2 Phase 1 north | Xinan Shangmaocheng – Guiyang Dongzhan | 32·1 | 16 | 20·43 | 2017-21 |